Quick answer
Install the CRDK29-03 delay element only in RMS-29 Mojave Green reload motors that use the 14-second adjustable delay. Set the delay before assembly, use the supplied insulators and spacers, and never substitute high-power RMS delay parts in mid-power hardware.
Why the CRDK29-03 is specific to certain reloads
The CRDK29-03 is a complete reload delay kit for RMS-29 Mojave Green motors with a 14-second adjustable delay. It includes the delay element plus insulators and spacers if needed, but other delay parts come with the RMS reload kit. Using it in a different motor or delay length can cause unreliable ejection.
High Power RMS reload delay kits are not compatible with Mid Power RMS products. Check your motor's RMS class before opening the kit.
When to set the delay
Set the adjustable delay before you install the element in the motor. Once assembled, adjusting the delay is difficult or impossible without disassembly. Confirm your desired delay time using your flight simulation or motor data, then follow the reload kit instructions for the adjustment method.
Step-by-step delay installation
- Verify motor compatibility: Confirm your motor is an RMS-29 Mojave Green reload with a 14-second adjustable delay. Check the reload kit label and the CRDK29-03 package. Do not use this kit in High Power RMS motors or in mid-power motors that require a different delay kit. If the motor is not RMS-29 Mojave Green, stop and use the correct delay kit.
- Set the delay length: Before installing the delay element, adjust the delay to your desired time using the method in your reload kit instructions. The CRDK29-03 is adjustable up to 14 seconds. Use a delay adjustment tool if required. Record your final delay setting so you can verify it after assembly.
- Install the delay element: Insert the delay element into the motor's delay cavity as directed by the reload kit instructions. Make sure it seats fully and squarely. Do not force it or damage the element. A delay element that does not seat flush may cause ejection failure.
- Add insulators and spacers: Install the supplied insulators and spacers only if your reload kit instructions call for them. The CRDK29-03 includes these parts if needed. Do not add extra parts or omit required ones. Compare the parts in your kit to the reload kit diagram before closing the motor.
- Final check: Re-check that the delay is set to the intended time and that all components are properly seated. Confirm that no parts are left out and that the motor is assembled according to the reload kit instructions. A second visual check before flight prevents most delay-related failures.
Product facts
- AeroTech RMS-29 Mojave Green Complete Reload Delay Kit - CRDK29-03: The CRDK29-03 is for use with RMS-29 Mojave Green reload motors using the 14-second adjustable delay and includes one delay element plus insulators and spacers if needed. This kit supplies only the delay components; you still need the main reload kit for the motor.

AeroTech RMS-29 Mojave Green Complete Reload Delay Kit - CRDK29-03